For cement, the second gate binds only locally: a new clinker line takes about 15 months where a Chinese turnkey contractor builds it (Kant, Kyrgyzstan, 0.8 Mt/yr: construction from early 2024, launched by June 2025) but about four years in the US (Heidelberg's Mitchell, Indiana: construction from 2019, first clinker 23 Apr 2023), while world kiln capacity sits in surplus, with China's 1.81 Bt/yr of clinker capacity running at an estimated 53% in 2024.

What's at stake, and why now

Evidence 7 passages

  • groundsSource document

    Heidelberg Materials is pleased to announce that the first clinker was produced at the company’s new state-of-the-art cement plant in Mitchell, Indiana, on April 23, 2023.
  • groundsSource document

    The construction of the new Mitchell cement plant began in 2019 and the vast majority of the work at the site has now been completed.
  • qualifiesSource document

    It will also help ease cement supply constraints in the industry, producing four times the amount of cement compared to the existing facility, with total annual cement production expected to be more than 2.4 million tons.
  • groundsSource document

    President Sadyr Japarov has launched a new 0.8Mt/yr clinker production line at the Kant Cement plant.
  • groundsSource document

    Construction of the dry-process line began in early 2024, with equipment supplied by China's Beijing Triumph International Engineering, a subsidiary of Sinoma.
  • groundsSource document

    It noted that the country has a production capacity of 1.81Bnt/yr and an estimated clinker utilisation rate of 53% in 2024.
  • groundsSource document

    In 2024, affected by the reduction of real estate investment and the slowdown of infrastructure projects, the cement industry in China was caught in a situation of insufficient demand and aggravated overcapacity.